Managing Director of Sanduao International Container Terminal Wang Xiaobin said the construction is divided into two phases. Phase 1 comprises two 100,000-tonne berths, which cost CNY1.3 billion (US$190 million) to build and will be completed by 2010. Phase 2 comprises two 200,000-tonne berths costing CNY1.8 billion and will be finished by 2012. Following completion, the terminal will have an annual capacity of 6 million TEU and be able to accommodate sixth-generation containerships.
Marine BizTV is the first 24 hour free to air Global Maritime Television Channel. Marine BizTV is spearheaded by a group of Naval Architects, Marine Engineers and Captains, who ensure that Marine BizTV is an informative, educative medium which is ideal for maritime business development and promotion.
Monday, April 6, 2009
Fujian's Sanduao box terminal starts construction
THE Sanduao International Container Terminal, which is situated in the Sanduao port area at southeastern China's Fujian province, has commenced construction.
Managing Director of Sanduao International Container Terminal Wang Xiaobin said the construction is divided into two phases. Phase 1 comprises two 100,000-tonne berths, which cost CNY1.3 billion (US$190 million) to build and will be completed by 2010. Phase 2 comprises two 200,000-tonne berths costing CNY1.8 billion and will be finished by 2012. Following completion, the terminal will have an annual capacity of 6 million TEU and be able to accommodate sixth-generation containerships.Read More
Managing Director of Sanduao International Container Terminal Wang Xiaobin said the construction is divided into two phases. Phase 1 comprises two 100,000-tonne berths, which cost CNY1.3 billion (US$190 million) to build and will be completed by 2010. Phase 2 comprises two 200,000-tonne berths costing CNY1.8 billion and will be finished by 2012. Following completion, the terminal will have an annual capacity of 6 million TEU and be able to accommodate sixth-generation containerships.